Bulletin Number

Chapter 5: Maintenance

21 of 36

Chapter 5: Maintenance

5-1 Preventative Maintenance Schedule

Check

Frequency

Knife clearance

Weekly

Knife retaining screws for tightness

Weekly

Knife exposure

Weekly

Shield retaining screws for tightness

Weekly

Screen retaining studs fro tightness

Weekly

Lubrication of drive motor bearings

Monthly

Lubrication of rotor bearings

Monthly

Screen Wear

Monthly

Belt Tension

Monthly

Hopper and cutting chamber screws are tight

Monthly

5-2 Lubrication

Lubrication of rotor bearings should be based on the size and type of bearing, the RPM at
which the rotor is turning, and the temperature at which the bearing is operating.

The size of the bearing will determine the amount of grease required. The RPM, bearing type,
and size of the bearing will determine the frequency of lubrication. Higher than normal
temperatures will determine the amount of grease required.

New Bearings

Bearings are initially lubricated at the factory prior to shipment. However, when assembling
new bearings and before bearing caps are installed, fill every third cavity of the bearing using
a hand grease gun, and then rotate the shaft by hand to distribute the grease. Fill the bearing
cavity 1/3 full of grease.

A hand-operated grease gun is preferred over a power grease gun because of better control of
pressure and quantity dispensed. This tends to prevent over-greasing and damage to seals.

Run the machine and observe drainage from the bearing housing. If a soupy discharge is
observed (indicating oil separation), then add a couple of sots of grease from a hand gun at
intervals until the discharge is no longer soupy.

Re-Lubrication

A new granulator rotor bearing should be greased after the first two weeks of operation, and
then re-lubricated every 2-4 weeks, depending on the duty cycle. Continuous operation (24
hours a day) at a maximum capacity would require lubrication every 2 weeks. Internittent
operation and/or light duty intervals could require lubrication every 4 weeks.