5.10.2 System Parameters Verification/Adjustment

The MX28B system control unit is delivered with pre-programmed parameter default settings.
A complete listing and description of all system configuration parameters as well as displayable
system status and information is provided in Section 6. Read Section 6 to gain an understanding
of and how to use the operational features provided by the MX28B dc power plant. As a
minimum, the following parameters should be verified and adjusted, if required, before
connecting batteries or loads to the power plant:

1) Battery Float Voltage - default = -54.00V dc (Check the manufacturer’s

recommendation for the batteries being used in the system.)

2) Battery Maximum Recharge Rate - default = 50A. (Bellcore specifications

recommend a maximum charging rate of battery capacity (in Ampere-hours) divided by
20 hours; check the manufacturer’s recommendation.)

3) System Voltage - measurement

≅ -54.00V dc (This is a measurement by the system of

the dc output bus voltage.)

4) LVD Option - default = “Enable” (If the MX28B does not have an LVD installed, this

should be changed to “Disable”.)

5) Rectifier Information - Check the rectifier information displays to verify that all

rectifiers installed can be viewed on the control unit display and that no rectifier alarms
are active.

Section 6 provides location information for these parameters and how to make changes if
required.

5.10.3 Full System Power Up

To complete a full system power up, perform the following steps

1) Turn OFF all the circuit breakers that supply ac power to the rectifiers in the MX28B dc

power plant.

2) Turn on the external circuit breaker from the battery to the power plant.

3) Turn on all the circuit breakers that supply ac power to the rectifiers in the MX28B dc

power plant.

4) Load circuit breakers and distribution fusses may now be turned on and inserted as

required.