41. Check and double check to make sure that all step
related with the front and rear end were performed
properly. Check and double check to make sure that all
stock and new hardware is torque to proper torque
specifications. Use the torque sheet at the beginning of
the installation manual.

42. Install the tires and wheels and safely lower the
vehicle to the ground.

43. Once the installation is complete, make sure to bleed
the brake lines. Also, using the proper brake fluid, make
sure to top off the brake fluid level.

CONGRATULATIONS INSTALLATION

Special Note: After the completion of the

installation, Tuff Country EZ-Ride

Suspension recommends taking the vehicle

to an alignment shop and having a proper

front end alignment performed.

It is also a good idea to keep a close watch

on the front and rear drive line U-joints. If

they start to wear out, make sure to replace

them.

If you have any questions or concerns,

please feel free to contact Tuff Country or

your local Tuff Country dealer.

Torque Settings

5/16”

15—18

ft

lbs.

3/8”

28—32 ft lbs.

7/16”

30—35

ft

lbs.

1/2”

65—85 ft lbs.

9/16”

85—120

ft

lbs.

5/8”

95—130

ft

lbs.

3/4”

100—140

ft

lbs.

the small end of the new block needs to be installed
with the small end towards the front of the vehicle.

Repeat procedure on passenger side.

See Illustration # 9

33. Raise up on both hydraulic floor jacks at the same
time until the driver and passenger side stock spring
assembly seats flush with newly installed 5.5” block.

34. Locate (4) new 5/8” x 2 3/4” x 14 1/2” square U-bolts,
(8) 5/8” U-bolt high nuts, (8) 5/8” U-bolt washers and the
stock upper U-bolt plates that were removed from step #
28. Working on the driver side, install (2) new 5/8” x 2
3/4” x 14 1/2” square U-bolts into the stock location and
secure using the new 5/8” high nuts and washers.
Torque to 130 ft lbs. Repeat procedure on passenger
side. Special Note: With a suitable cutting tool, cut
off the excess U-bolt threads on all (4) rear U-bolts.

See Illustration # 9

35. Working on the driver side, install the new rear
shocks absorbers using the stock hardware removed
from step # 27. Special Note: Shocks are not included
with this suspension system, shocks need to be
ordered as a separate part number, Tuff Country EZ-
Ride Suspension recommends using a 30” fully
extended nitrogen gas shocks.
Repeat procedure on

passenger side.

See Illustration # 9

36. Place a pair of hydraulic floor jacks under the stock
transfer case cross member. Place one hydraulic floor
jack on the driver side and one on the passenger side.
Carefully raise up on both hydraulic floor jacks at the
same time until they come into contact with the stock
transfer case cross member.

37. Working on the driver side, remove the stock
hardware that connects the stock transfer case cross
member to the stock frame rail. The stock hardware may
be discarded. Repeat procedure on the passenger side.

38. Carefully lower down on both hydraulic floor jacks at
the same time approximately 2”. This will allow enough
room for the new transfer case drop kit to be installed.

39. Locate (2) transfer case drop tubes, (4) 7/16” x 3”
bolts, (4) 7/16” flat washers and (2) 7/16” unitorque nuts.
Working on the driver side, install the new transfer case
drop tube between the stock transfer case cross member
and the stock frame rail. Secure using the new 7/16” x
3” bolts and hardware. Torque to 35 ft lbs. Special
Note: The transfer case drop tubes are the tubes that
measure 1 1/2” tall.
Repeat procedure on the

passenger side.

See Illustration # 10

40. Carefully remove both hydraulic floor jacks from
under the transfer case cross member.