50. Locate (2) new rear lifted blocks. Working on the
driver side, install the new rear lifted block between the
stock axle and the stock spring assembly. Special Note:
The new rear lifted block has a slight taper to it,
make sure to install the new rear lifted block with the
smaller end towards the front of the vehicle.
Repeat

procedure on the passenger side. Carefully raise up on
both hydraulic floor jacks at the same time until the newly
installed lifted blocks seat properly with the stock spring
assembly. Special Note: Make sure that the nipple on
the new rear lifted block seats properly into the
stock spring perch.

See Illustration # 10


51. Locate (4) new 5/8” x 3 5/8” x 14 5/8” Round U-bolts,
the stock upper U-bolt plates that were removed from
step # 47, (8) new 5/8” U-bolt high nuts and (8) new 5/8”
U-bolt washers from hardware bag 58NW. Working on
the driver side, install the stock upper U-bolt plate into
the stock location. Install the new U-bolts into the stock
location and secure using the new 5/8” x 3 5/8” x 14 5/8”
round U-bolts and hardware. Torque to 130 ft lbs.

Repeat procedure on the passenger side.

See Illustration # 10


52. Locate the new rear shocks and the stock shock
hardware that was removed from step # 46. Working on
the driver side, install the new shock into the stock upper
and lower location and secure using the stock hardware.
Torque to 75 ft lbs. Repeat procedure on the passenger

side.

53. Carefully remove both hydraulic floor jacks from
under the rear axle.

54. Check and double check to make sure that all steps
were preformed properly. Check and double check to
make sure that all stock and new hardware is torque to
proper torque specifications. Special Note: Refer to the
owners manual and the torque setting sheet at the
end of the installation manual.

55. Install the tires and wheels and carefully lower the
vehicle to the ground.


Congratulations, Installation

Complete

Once the installation is complete, take the

vehicle directly to an alignment shop for

proper front end alignment.

Special Post Installation Procedure: Make

sure that the new mounting hardware that

connects the new twin “I” beam axle pivot

drop brackets to the stock location are

check every 3000 miles for proper torque, if

these bolts are not properly torqued, they

will loosen up and could cause serious

damage to the new twin “I” beam axle pivot

drop brackets and or vehicle. Tuff Country

EZ-Ride Suspensions take no responsibility

for improper installation or improper post

installation procedure.

If you have any questions and or concerns,

please feel free to contact Tuff Country EZ-

Ride Suspension. (801) 280-2777

Torque Settings

5/16”

15—18

ft

lbs.

3/8”

28—32

ft

lbs.

7/16”

30—35

ft

lbs.

1/2”

65—85

ft

lbs.

9/16”

85—120

ft

lbs.

5/8”

95—130

ft

lbs.

3/4”

100—140

ft

lbs.