70. Install the tires and wheels and carefully lower the vehi-
cle to the ground.

71. Working on the driver side, move back to the stock hard-
ware attaching the upper and lower control arms to the newly
installed bracket and add some thread locker or loctite and
torque to 210 ft lbs. Now add some thread locker or loctite
to the stock upper and lower control arms where they are
attached to the axle mounts and torque to 210 ft lbs. Repeat
procedure on the passenger side.

72. Working on the passenger side, install the stock track bar
into the newly installed track bar relocation bracket and
secure using the stock hardware. Make sure to use thread
locker or loctite and torque to 130 ft lbs.

73. Working on the driver side, add some thread locker or
loctite on the lower track bar hardware and torque to 130 ft
lbs.

74. Working on the driver side, add some thread locker or
loctite to the hardware attaching the sway bar end links to the
newly installed bracket and torque to 80 ft lbs. Repeat pro-
cedure on the passenger side.

75. Working on the driver side, re-install the parking brake
bracket to the driver side lower control arm. Special note:
we just want to make sure that the passenger side cable
is in the bracket and the driver side cable is loose.
Add
some thread locker or loctite and torque to 35 ft lbs.

76. Working on the driver side and referring to the picture,
trim the liner horizontally on the angled face about the area
of contact. Leave the two fasteners intact and trim the liner
at an angle on each end to meet the bottom of the liner. Now
paint any exposed surfaces. Repeat procedure on the pas-
senger side. Special note: This step only needs to be per-
formed if contact occurs with the new tires and plastic
liner.

Tuff Country EZ-Ride Suspension recommends that a
complete re-torque is done on all bolts associated with
this suspension system. It is the customers responsibil-
ity to make sure that a re-torque is performed on all
hardware associated with this suspension system after
the first 100 miles of installation. It is also the customers
responsibility to do a complete re-torque after every
3000 miles or after every off road use. Neglect of follow-
ing these steps could cause brackets to come loose and
cause serious damage to the suspension system and to
the vehicle.

Tuff Country EZ-Ride Suspension packages (2) sets of
instruction sheets with this box kit. (1) is for the installer
and (1) is for the customer. The (1) for the customer has
some post installation procedure literature and it is the
installers responsibility to make sure that the customer
receives a copy of the installation manual along with the
literature.

If you have any questions or concerns, please feel free
to contact Tuff Country or your local Tuff Country deal-
er.