Functional Test

Pre-startup Procedures

1. Ensure all DC and AC breakers or fuses are disconnected.

2. Double-check all wiring connections.

3. Inspect the work area to ensure tools or debris have not been left inside.

4. Verify battery voltage using a digital voltmeter (DVM). Confirm the voltage is correct for the

inverter model. Confirm the polarity.

5. Connect the system display (if present).

Startup

If steps are inapplicable, they can be omitted. However, it is highly
recommended that all applicable steps be performed in the
following order.

If the results of a step do not match the description, see the
Troubleshooting section on page 31.

To start the system:

1. Close the main DC breaker (or connect the fuse) from the battery

bank to the inverter. Repeat for every inverter present.

2. Observe the LEDs in the AC wiring compartment. One of the

three BATTERY LEDs should be illuminated — green, yellow, or
red. Any of them are acceptable at this stage. (See page 11 for a
description of the LEDs.) The INVERTER LED (green) may come
on at this time. The fan will run briefly and the relay will click as a
self-test.

3. The ERROR LED may flash briefly. If it remains illuminated or

continues to flash during any step, proceed immediately to
page 31 for troubleshooting.

4. Confirm that the system display is operational. (See the system

display manual for a description of the menu items that appear
on a correctly functioning display.)

Figure 2

AC Wiring Compartment

CAUTION: Equipment Damage

Incorrect battery polarity will damage the inverter. This damage is not covered by the warranty.