Installing the new water heater (cont’d), Venting (cont’d) – State PR6 75 XRVIT User Manual

Page 20

Advertising
background image

CONNECTING VENT TO BLOWER

1. If making an immediate horizontal run of vent off the

blower, a 3

″ PVC, ABS or CPVC Schedule 40 elbow

(supplied locally) is required. Place the elbow in the

required direction on the blower and using 3 sheet metal

screws, attach the elbow.

INSTALLATION SHOWING USE OF PVC, ABS OR

CPVC PIPE

2. If there is to be a vertical run of vent from the blower, the

3

″ PVC, ABS or CPVC pipe must be attached to the blow-

er using 3 sheet metal screws.

EXTERIOR WALL

SILICONE

SEALER

SILICONE SEALER

SCREW

SCREW

SCREW

SCREW

SCREEN

COLLAR

VENT CAP MUST

BE POSITIONED

DOWNWARD

1

1

2

MIN. EXTENSION

THROUGH

EXTERIOR WALL

COLLAR

SEAL WITH RTV

SEALANT

SEAL WITH RTV

SEALANT

Venting (cont’d)

Installing the New Water Heater (cont’d)

CUTTING OPENING THROUGH AN OUTSIDE WALL

AND COLLAR INSTALLATION

After reading the manual and you have determined the

location of the opening in the wall, (using the drawing

below), cut a 2

1

2

″ hole for 2″ vent piping, 3

1

2

″ hole for 3″

vent piping or a 4

1

2

″ hole for 4″ vent piping hole through an

exterior wall.
NOTE: When determining location of the opening in the

outside wall allow for the

1

8

rise per five feet that has

taken place in the horizontal run.

MIN. RISE

1

8

PER FIVE FEET

CL OF FLUE

40 GAL.– 60

50 GAL.– 59

1

2

75 GAL.– 63

14

″ MIN. 40,000 BTU/HR

12

″ MIN. ALL OTHER MODELS

The 3

″ (or optional 2″ and 4″) PVC, ABS or CPVC Schedule

40 vent pipe can be run from the water heater through the wall

or from the wall to the water heater, whichever is most con-

venient. The vent pipe must extend a minimum of 1

1

2

″ through

the exterior wall. Extending the vent cap as far as possible from

the surface of the exterior wall will help minimize discol-

oration of the wall in this area which may be caused by the

flue gases. Note that the inside collar must be slipped over

the vent piping before locating the pipe through the wall.

Before securing the inside and outside collars to the wall, use

a silicone sealer between pipe and opening to insure a water

and air tight seal.

20

3. If the optional 2

″ vent piping is to be used (40,000

BTU/Hr. models only), the 2

″ street elbow, 3″ to 2″ reduc-

er and 3

″ (minimum) section of 3″ PVC, ABS or CPVC

pipe must be supplied locally. The 3

″ (minimum) section

of 3

″ PVC, ABS or CPVC pipe must be attached to the

blower using 3 sheet metal screws.

Advertising