This document contains the recommended procedures for installing a Hawkeye Industries Sparrowhawk Gauge Head.

Requirements

Ensure that the tank is prepared to accept a Sparrowhawk Gauge

Head (per Tank Preperation Instructions,) and has been fitted with

a float and float guide kit.

Contents

Tools

Parts Required

A.) Installing Sparrowhawk Gauge Head

A.) Installing Sparrowhawk Gauge Head

Thread the float cable, cut end first, around the reel of the gauge head in

the direction shown.

Feed the stud end of the float cable through the gauge head coupling

down into the tank.

Secure the cut end of the float cable in position so that it does not slide

back through the gauge head.

TANK PREPARATION | GAUGE BOARD KIT INSTALLATION | FLOAT GUIDE KIT INSTALLATION |

GAUGE HEAD INSTALLATION

| GOSHAWK INSTALLATION

Installation Instructions

Sparrowhawk Gauge Head

QTY

Part

1

Sparrowhawk Gauge Head

1

Float Cable Assembly for specified tank height

TAPE OR CLAMP

IN PLACE

1.)

2.)

3.)

4.)

Sparrowhawk Instructions, September 2013

1

Apply thread sealant to the 1½ NPT threads of the gauge head and

tighten it into the 1½ NPT coupling on the tank with a pipe wrench. Ensure

that the open side of the gauge is aligned with the gauge board and faces

towards the board.

APPLY THREAD SEALANT