1. Locate mixing valve in a suitable place

accessible for servicing and adjusting. Valve
should be as close as possible to point of use.

2. Thoroughly flush supplies.
3. Connect Hot and Cold supplies to mixing valve

inlets and outlet to fixture(s). Supply lines
by others.

4. Turn on supplies and inspect for leaks. Tighten

connections if leak(s) are detected.

5. Turn on fixture and allow to run until water

temperature stabilizes. Measure water
temperature. If water is not at desired
temperature adjust as needed, (refer to
adjustment section below).

1. Loosen locknut. Detail A
2. Turn on fixture so temperature can stabilize.
3. Using allen wrench turn adjustment stem

counter-clockwise for hotter or clockwise for
colder outlet temperature. Detail B

4. Tighten locknut to prevent any unauthorized

or accidental temperature adjustment.

5. Re-check temperature.

INSTALLATION:

TEMPERATURE ADJUSTMENT:

Acorn Controls

Division of Acorn Engineering Company

®

, A member of Morris Group International

Manual #7802-114-000

Date: 04/01/13

DETAIL A

DETAIL B

PROVIDED,

BALL VALVES

SHIPPED LOOSE

INSTALLER

PROVIDED

SUPPLIES

INSTALLER

PROVIDED RISER

AND CONNECTIONS

WRENCH

LOCKNUT

ALLEN

WRENCH

ADJUSTMENT

STEM

TYPICAL INSTALLATION