If the first corner panel is supported by a 1" vinyl
sealer (screed), seek assistance to support the
corner panel in a vertical position until succeeding
wall panels are installed. Wall and corner panels
do not lock to the vinyl sealer (screed).

Select the next panel as indicated on the floor
plan and position it on the floor or sealer (screed)
close enough to the first panel installed so that
section latch engagement is possible.

Making sure that the two panels are perfectly
aligned at the TOP EDGE and that the VERTICAL
JOINT of the two panels are perfectly flush, turn
the section latches on the vertical edge of the panel until they are completely
engaged.

IMPORTANT! Insist that the top edges of the adjoining panels are aligned
perfectly.

If misalignment is encountered, merely lift the lowest panel edge while
locking to achieve alignment and, when all latches are engaged, permit the
locked panels to resume their normal position on the walk-in floor or sealer
(screed).

dO NOT SHORT-CUT! TAKE ENOUGH TIME TO PROPERLy ALIGN ALL
SECTIONS.

W

alk

-i

n

i

nsTallaTion

-W

all

& c

eilinG

P

anel

e

RecTion

Correct

Misalignment