Chapter 1: installation and assembly – Pathway LR Installers Guide User Manual

Page 4

Advertising
background image

DMXPathfinder LR

Installation & Assembly

3

Chapter 1: Installation and Assembly

S

UMMARY

This section describes how to correctly assemble the DMXPathfinder LR

hardware into an equipment rack and connect permanently installed external
wiring.

To ensure a trouble-free installation, you should follow this sequence:

1. Install the equipment rack
2. Run conduit and pull cable
3. Install auxiliary rack equipment and power bars
4. Mount termination boards (if applicable)
5. Dress cable in the rack and terminate (if possible)
6. Unpack the DMXPathfinder LR I/O Modules and prepare
7. Install the I/O Modules in the rack
8. Connect cabling to the I/O Modules
9. Power up and test

B

EFORE

S

TARTING

Before installing the DMXPathfinder LR equipment rack, you should

carefully consider the environment in which the equipment is to be installed, the
proximity to power sources, and the required conduit and/or cable runs.

Environmental Considerations -- To maximize equipment life and minimize

the possibility of unreliable operation or failures, the following conditions should
be adhered to:

Ambient temperature extremes: -10 to 50 degrees C

Recommended operating temperature: +10 to +40 degrees C

Relative humidity: 10-95% non-condensing

General conditions: clean, dust-free environment

Fan Cooling -- Each of the DMXPathfinder LR Output Modules is provided with

an internal cooling fan. These fans draw air in on the right hand side and
exhaust air on the left. To ensure adequate air circulation, do not block the
modules at either side. If more than two or three Output Modules are installed in

Advertising