Heat Controller Multi-Position Air Handler with Hydronic Heat with PSC Motor

HWCGxxT0A

6

Counter Flow Installation

Fig.7. Air Handler parts and changes for Counter flow

Before positioning the Air Handler in the counter

flow position, remove lower access panels, filter

panel and filter.

Remove the A-Coil assembly with the horizontal

drain pan; discard the horizontal drain pan (not

required for counter flow application).

Rotate the Air Handler 180° to the counter flow

position.

Remove the coil deck and filter channel, rotate

the filter channels 180° and re-attach in the

same location they were removed from.

Rotate the coil deck 180° and re-attach in the

holes near the center of the cabinet (screws not

provided).

Slide the A-coil assembly into the cabinet on the

coil deck (without the horizontal drain pan).

Note: Push the coil pan assembly all the way to

the rear of the cabinet until it locks under the

bracket in the rear.

Place the 3” x 16” counter flow plates at the

outside bottom of the coil as shown in FIG. 8.

Replace the access panels and filter panel.

3" X 16" Metal Plate

Fig.8. Position of plates required in counter flow

Electrical Installation

These units are designed for single or three phase 120

volts, 60 Hz power supply. Wire selection and wiring

must be in accordance with the National Electric Code

(or CEC for Canadian installations) and/or local codes.

Unit terminals are designed to accommodate copper and

aluminum wirings. If aluminum wiring is used; please

observe special precautions relative to sizing, wire

connections and corrosion protection.

Fig.9 shows the typical electrical connections required

for A/C only and heat pump applications.

The unit ships with a micro-processor based board

which controls the electrical functioning of the unit. An

inspection of the controls is recommended prior to start-

up.

Fig.10 provides a schematic of the control board present

in the unit. The units ship from the factory with the

aquastat jumper in the OFF position (right two pins) and

the heating selector in the HW position (right two pins). If

an aquastat is used in the application; the jumper should

be changed to ON position (left two pins).

Note:

Terminals T and N located on the top right side

of the board are not intended for field use and should be

left unconnected.

CAUTION

The aquastat (AQ) jumper must be

in the OFF position at all times; except for when an

aquastat is used in the application. If the jumper is

moved to the ON position without installing an aquastat

the blower will not be energized.

When an aquastat is present, the blower will be

energized at the aquastat temperature settings.

Fig 9. Electric connections

CAUTION

This model is shipped without factory a installed pump,

therefore the two black wires should be connected to the

boiler terminals T T. In applications where a boiler is

used to provide the hot water supply, these wires shouId

7

be connected to the boiler. Terminals T T are normally

open dry contacts.

In applications where a valve is used to regulate hot

water supply, the two black wires located on the T T

terminals should be removed and placed on the two

terminals reading “VALVE”. The open ends of the wires

should be connected to the valve according to local

requirments and instructions of the valve manufacturer.

On call for heat, 24V will be sent to the field installed

valve or pump relay.

Fig.10. Micro-processor control board

On call for heat water will circulate through the water

(hydronic) coilfor 60 secs prior to energizing the blower.

After the thermostat is satisfied, the blower will continue

to stay energized for a minimum of 30 sec. This helps

maximize heating efficiency.

The freeze protection sensor is connected to the FP and

R terminals. These are normally open and will close

when the sensor sees 40ºF. The pump stays ON for a

minimum of 30 sec.

The board has an built-in timer which circulates hot

water 6 times a day for 60 sec each time to prevent the

coil from freezing.

Start up

WARNING

The hot water (hydronic) coil and

all water lines

MUST be purged of air prior to starting the

pump. Failure to do so could result in pump damage.

Manufacturer will not be responsible for any property or

physical injury caused by failure to follow this instruction.

WARNING

Hot water flowing to the coil

should be in the range of 120º - 180º F. Water at these

temperatures can cause first-degree burns. Use of

proper saftey gear while installing or servicing the

equipment is strongly recommended, as is installation of

a water-tempering valve (for water temperatures of

above 140ºF) to supply lower temperature water to

fixtures in the house. N170L series or equivalent should

be used.

Connect the hydronic coil to the water heater system as

shown in Fig 11. Use flexible piping and insulate all

pipes. Plumbing must be in compliance with state or

local codes (Code CMR248 in Massachusetts). The

units for hydronic heat have different top and heater box

configurations. This configuration is not suitable for

electric heat.

DO NOT try to install a hydronic heater in a

unit not equipped for it. Verify connections: hot water to

“in” and cold water to “out”. 7/8” ODstubs are provided

for plumbing connections. Bleed the air flow system

through the bleeder port or optional valve.

Purging The System

1) Open air vent and allow water heater to fill with

water. Close air vent when water heater is full and

all air has been purged.

2) Ignite water heater. Set thermostat on water heater

to 140 degrees.

3) Close the valve on the hot water supply from the

water heater ("A") and open the valve on the cold-

water return to the water heater ("B"). Then open the

air vent in the fan coil. Use a bucket or hose to

discard water during purging process at air bleed

valve. Purge air completely from line.

4) Once air is purged, close return valve ("B") and open

supply valve ("A"). Purge the coil and lines of air

completely.

5) After air is purged from the system and filled with

water, open the return valve ("B") and the supply

valve ("A"). Then close the air vent in the fan coil.

6) Apply power to the fan coil and set the room

thermostat on heat. Raise the temperature setting to

activate the circulating pump

7) Check the pump to ensure proper operation. The

water inlet of the unit should be hot if the water