Iv. packaged boiler assembly, Warning – Burnham Independence IN10 User Manual

Page 15

Advertising
background image

15

Figure 22: Securing Draft Hood to Canopy

A.

Remove crate and move boiler to permanent position

as detailed in Section III: Semi-Pak Boiler Assembly.

B.

Remove Jacket Front Panel. See Figure 45.

C.

Remove poly bag from vestibule area.

D.

On Steam Boilers with probe low water cutoff the

L404 pressure limit/control has been packed in the

vestibule area.
1. Screw the pressure limit/control onto the syphon.

DO NOT TWIST CONTROL. Use wrench on hex

fitting at bottom of control. See Figure 18.

2. Snap the electrical conduit from the adjacent

junction box into the hole in the control.

3. Open the control's clear cover and attach the two (2)

wires in the conduit to the two (2) unused screw

terminals.

IV. Packaged Boiler Assembly

Figure 21: Draft Hood Attachment

E.

Install Jacket Front Panel.

F.

Install Draft Hood. Models IN3 through IN9.

1. Locate and open "Rear Draft Hood Carton".
2. Position Draft Hood on Canopy Rear Flange. See

Figure 21. Top canopy flange must fully engage

"U"-shaped draft hood flange for proper installation

and operation. Care must be taken to assure that

draft hood is level.

3. Secure Rear Draft Hood to Canopy with wing nuts

provided. See Figure 22.

WARNING

Installation of this boiler should be undertaken

only by trained and skilled personnel from a

qualified service agency.

WARNING

Do not alter boiler draft hood or place any

obstruction or non-approved damper in the

breeching or vent system. Flue gas spillage can

occur. ETL/ETLC certification will become void.