5

Fig. 10 Single pump and overflow.

Fig. 11 Double pumps require a third

hole for overflow assembly.

• Remove any sharp objects from the

excavated hole that may damage

the liner.

• Unfold the underlayment fabric and

place it into your excavated pond.

Starting from the bottom, remove

the slack from the underlayment,

making sure it conforms into all of

the elevations.

• Place the EPDM Fish-Safe liner on

top of the underlayment.

(See fig. 9)

• The installation process is the same

as the underlayment, starting at the

bottom and contouring the liner up

and out of the pond.

• Try to get the large folds out, but

the main goal is to make sure that

it’s lying flat and going into all cor-

ners. Don’t try to get it perfect—you

will hide the liner with rocks and

gravel later.

• Make sure the liner is high enough

around the edges of the pond. This

should not be a problem if you mea-

sured out the pond and excavated

it correctly. Problems can be fixed

by readjusting the liner into the

excavation, backfilling (making the

pond smaller) in areas where there

is not enough liner, or simply buying

a larger liner.

Fig. 9 Place the liner on top of the

underlayment following the same

installation procedures. Make

sure liner is positioned in such a

way that allows it to extend and

completely cover the opening on

the BIOFALLS

®

filter.

Install Underlayment and Liner

STEP 5

Excavate your Pond cont …

1st plant and rock shelf:

shelf varies 8" or greater wide,

1" to 12' deep
Set 6" to 12" size cobblestones

on vertical edges. Gravel on all

horizontal surfaces

2nd plant & rock shelf:

16" to 20" deep

Plant pocket 6" to 8" deep,

10" to 16" diameter

Water line

Marginal plants should be removed

from containers and placed directly

into the gravel

Liner ends 1" to 2'

outside of pond

Mulch

Fig. 8 Pond excavation - side view of plant pockets.

Installing the Skimmer and Overflow Installation

STEP 6

• Install the two bulkheads into the

back of the Signature Series

Skimmer prior to dropping into

the excavated hole. The filter has

two openings on the back allowing

several plumbing options.

1. For single pump applications, the

pump plumbing line attaches into

one bulkhead and the overflow

is attached to the other. Use

the angle of the bulkheads to

your advantage by choosing the

bulkhead that works best with

the direction and sweep of the

plumbing to the BIOFALLS

®

filter.

(See fig. 10)

2. For double pump applications,

each pump will hook up to one of

the bulkheads. A 3rd hole

will need to be drilled in the back

of the skimmer if you desire to

add an overflow. A drill point

guide can be found on the head of

the frog within the logo. Use a 3

inch hole saw to drill the opening

for another bulkhead fitting

(sold separately).

(See fig. 11)

• Follow the same bulkhead installa-

tion steps used when installing the

bulkhead on the BIOFALLS

®

filter.

(see bulkhead assembly).

• Install the PVC slip fitting into each

bulkhead on the outside of the skim-

mer to receive the pump plumbing

and overflow plumbing.

Bulkhead

Adapter

Nut

Plastic

Washer

Rubber

Gasket

Bulkhead

Flex PVC

Bulkhead assembly.