Electrical installation 3 – Lenze MDxMA Three-phase AC motors ATEX 3D category User Manual

Page 8

Advertising
background image

Electrical installation

3



8

BA 12.0031 EN 2.1

PE conductor connection
At the PE conductor connection in the terminal box and on the housing of the motor, the

PE conductor must be connected by placing a plain washer between cable lug and housing

of the motor. A serrated lock washer between cable lug and screw head / hexagon nut

ensures an electrically well-conductive connection. The following illustrations show the

correct connection for the different designs of the PE conductor connections:

1

2

3

4

Fig. 2

Earth connection at housing and in terminal box
1

Washer

2

Earth connection cable lug

3

Serrated lock washer

4

Screw

1

2

3

4

5

6

Fig. 3

Earth connection via terminal stud in terminal box
1

Terminal stud

2

Earth symbol

3

Washer

4

Earth connection cable lug

5

Serrated lock washer

6

Hexagon nut

Selection of cable gland
The threadedholesofthe terminal box are closedusinghigh-qualityscrewplugswithseal.
To insert the supply conductor in the terminal box, the corresponding screw plug is

replaced by a cable gland with strain relief. For this purpose, it is necessary to select a cable

gland that is certified for explosion protection and features at least enclosure IP54.