Commissioning and operation

Important notes

7

l

42

BA 33.0005−EN 2.0

7

Commissioning and operation

7.1

Important notes

For trial run without output elements, lock the featherkey. Do not deactivate the
protective devices, not even in a trial run.

Check the correct operation of the brake before commissioning motors with brakes.

7.2

Before switching on

)

Note!

Before switch−on, you must ensure that the motor starts with the intended
direction of rotation.
Lenze motors rotate CW (looking at the driven shaft) if a clockwise three−phase
field L1

W U1, L2 WV1, L3 W W1 is applied.

Before initial commissioning, before commissioning after an extended standstill period, or
before commissioning after an overhaul of the motor, the following must be checked:

ƒ

Measure the insulation resistance, in case of values

£1 kWper volt of rated voltage, dry

the winding.

ƒ

Have all screwed connections of the mechanical and electrical parts been firmly
tightened?

ƒ

Is the unrestricted supply and removal of cooling air ensured?

ƒ

Has the PE conductor been connected correctly?

ƒ

Have the protective devices against overheating (temperature sensor evaluation)
been activated?

ƒ

Is the controller correctly parameterised for the motor?
(

, Controller operating instructions)

ƒ

Are the electrical connections o.k.?

ƒ

Does the motor connection have the correct phase sequence?

ƒ

Are rotating parts and surfaces which can become very hot protected against
accidental contact?

ƒ

Is the contact of good electrical conductivity if a PE connection on the motor housing
is used?