Titus Electric Heat IOM User Manual

Installation manual

Advertising
background image

Installation Manual

EHeat-IOM-1.0

6-1-01

Electric Coil Installation, Operation, and Maintenance Manual

(For use with Titus Electric Coils manufactured after June 2 001)

General Information

All fan terminals with electric coils are ETL listed.

All single duct electric coils are ETL listed.

All electric coil control enclosures meet NEMA 1.

Single point power connection.

Installation

All terminal units with electric coils are designed to be

mounted in a horizontal plane with regard to the UP arrow

marked on the product label.

Always inspect electric coils for damage prior to applying

power.

Use copper conductors only.

All field wiring must conform to NEC and local building

codes.

Phase rotation of the incoming power is recommended

when connecting three phase electric coils to balance

building loads.

Always allow a minimum clearance of 36” in front of all

electric coil enclosures.

All terminal units must be properly grounded per NEC 424-

14 and 250.

Always check product label for voltage and current data to

determine proper wire size and current protection.

These recommendations are not meant to preclude NEC

requirements or local building codes that may be

applicable, which are the responsibility of the installing

contractor.

Fan Terminal Unit with Heater

Single Duct Terminal Unit with Heater

CAUTION

ELECTRIC SHOCK MAY RESULT

1. DISCONNECT POWER BEFORE

SERVICING UNIT.

2. DO NOT OPERATE UNIT WITHOUT

CONTROL COVER INSTALLED.

Advertising