Initial Test Set Up

Baseline Test Procedure (Refer to Figure 3)

1.0 Recommended Equipment

1.1 Two Isolated DC power supplies - 0 – 60 V; 10 A

1.1.1 If the DC power supply outputs are not isolated,

two 10 A 100 V Schottky diodes are required,
as shown in Figure 4.

1.2 DC electronic load - 10 A minimum.
1.3 Digital Multimeter

1.4 Oscilloscope.
1.5 Appropriately sized interconnect cables.
1.6 Safety glasses.
1.7 PI2003 Product Data sheet.

Figure 3 – Layout configuration for a typical redundant power application, using isolated power supplies.

Figure 4 – Layout configuration for a typical redundant power application, using non-isolated power supplies.