MODEL 17000 BULK TANK GAUGE

INSTALLATION AND OPERATING INSTRUCTIONS

Mount the 17000 bulk tank gauge in the outlet between the storage tank and the suction side of a

chemical pump (if applicable). When making up gauge to process lines, tighten connections by

placing the wrench on the square block at the end of the gauge. Do not tighten connections by

twisting gauge frame. If the top of the gauge is below the maximum possible liquid level or if there is

a possibility of pressure or vacuum in the storage tank (other than atmospheric pressure), the vent

connection on top of the 17000 should be connected to the upper part of the storage tank. A valve

should be installed between the storage tank and the 17000.

If your 17000 bulk tank gauge was ordered with a rate scale, you can check your pump rate by

closing the valve between the storage tank and the 17000. Observe the change in fluid height in the

17000 after 1 minute. Multiply the number of divisions observed by the rate per division to obtain the

pumping rate. Adjust pump and check rate again if necessary.