6.1 Initial commissioning

Normally, the pumps have already been test-run with
water.
Unless special agreements have been reached, there
may still be some residual amounts of water in the
pump. This must be noted in view of a possible
reaction with the medium.
Long life grease lubrication
The ball bearings are greased for life. Regreasing
is not possible and not necessary.
For service lives, see Section 7.2.

Oil bath lubrication:
Pour in oil into the bearing pedestal!
For procedure and the oil grade, see Sections 7.2
and 7.8.5
.

6.1.1 Filling the pump housing

Check to see whether the screws on the suction
flange, discharge flange, housing flange and drain
flange are tightened. When retightening the
housing screws, make sure that the support
bracket is undone. Otherwise, the pump could be
deformed.
For screw tightening toques, see Section 1.1.
Open the suction line fully so that the medium can
flow into the pump.
Open the discharge valve so that the air in the
pump can escape.
If air cannot be vented into the discharge line, e.g.
a drop in pressure in this line is not permitted,
venting must be performed upstream of the
discharge valve.
Monitor the venting operation until no air but only
liquid emerges.
Turn the pump shaft at the coupling several times.
Monitor the venting operation again until no more
air emerges.
Close the discharge valve again until
only the minimum flow rate is obtained
after the motor has been started.

6.1.2 Start-up

Check to see whether the pump shaft can be
readily turned by hand.
Check the direction of rotation of the motor with
the coupling disengaged or with a rotary field
instrument.
As viewed from the motor, the direction of rotation
of the pump is clockwise. See also the direction
of rotation arrow
of the pump.

The pump must not run dry during the check of the
direction of rotation.

Check alignment of the coupling.
Mount coupling guard.

The pump must be completely filled with
liquid.

The maximum admissible flow rate must not be
exceeded.

Otherwise the plain bearings can run dry in
both cases.

Switch the motor on.
Set the desired flow by opening the discharge
valve.

When the motor is running but the pump is not
conveying, this means that the magnetic drive has
stopped.

Switch motor off immediately in order to prevent
overheating of the magnet assemblies.

Then proceeded as follows:

Close discharge valve down to the position
"minimum flow rate"
Start motor again.

If the magnetic drive stops again, look for the cause.

6.2 Operating limits

The operating limits of the pump/unit in
terms of pressure, temperature, power and
speed are entered in the data sheet and it is

imperative to observe them!

6.2.1 Abrasive media

If liquids with abrasive constituents are
conveyed, increased wear at the pump is to
be expected. The inspection intervals should

be reduced compared with the usual times.

6.2.2 Min./max. flow rate

The operating range generally recommended lies at
0.3 Q

opt

to 1.1 Q

opt

. Consult the manufacturer for

operation outside this range and observe Section
2.6.2.