Installation pak 200 – Tweco Pak 200 User Manual
Page 43
Manual 0-5057
3-17
INSTALLATION
INSTALLATION
PAK 200
NOTE
Depending on the length of the torch leads, the system may require more coolant after turning the
system ON for the fi rst time.
a. Place the ON/OFF Switch to ON.
b. After about 30 seconds the system may shut down if the leads are not full of coolant.
c. Place the ON/OFF switch to OFF.
d. After 10 seconds place the ON/OFF switch to ON again.
e. Repeat steps ‘b’ through ‘d’ until the system no longer shuts down. Depending on the length of
the torch leads this sequence may need to be done three to fi ve times.
f. After the system stays operational allow the pump to operate for ten minutes to properly purge
any air from the coolant lines before using the system.
4. Re-fi ll the reservoir and re-install the fi ller cap.
5. Purge coolant from the torch before fi ring the torch. Ensure there are no leaks before use. If leaks are evident,
consult the coolant leak trouble-shooting guide in the maintenance section of this manual.