Rfsdv24/34 freestanding direct vent gas fireplace, Vertical through-the-roof applications, Vertical through-the-roof installation – Vermont Casting RFSDV24 User Manual

Page 14

Advertising
background image

14

RFSDV24/34 Freestanding Direct Vent Gas Fireplace

10003550

If the foundation is recessed, use recess brackets (not
supplied) for securing lower portion of the snorkel.
Fasten brackets to wall first, then secure to snorkel
with self drilling #8 x 1/2 sheet metal screws. It will be
necessary to extend vent pipes out as far as protruding
wall face. (Fig. 21)

Do not back fill around snorkel. A clear-
ance of at least 4” (102 mm) must be main-

tained between snorkel and the soil.

BG401

Snorkel

2/10/99 djt

Snorkel

Wall Screws

Foundation Recess

Recess Brackets

Watertight Seal

Around Pipe

Sheet Metal

Screws

BG401

Fig. 21 Snorkel installation, recessed foundation.

Vertical Through-the-Roof Applications

This Gas Fireplace has been approved for:

Vertical installations up to 40’ (12 m) in height. Up
to a 10’ (3 m) horizontal vent run can be installed
within the vent system using a maximum of two 90°
elbows.

Up to two 45° elbows may be used within the
horizontal run. For each 45° elbow used on the
horizontal level the maximum horizontal length must
be reduced by 18” (457 mm).

Example: Maximum horizontal length
0 x 45° elbows = 10’ (3 m)
1 x 45° elbows = 8¹⁄₂’ (2.6 m)
2 x 45° elbows = 7’ (2.1 m)

A minimum of an 8’ (2.4 m) vertical rise.

Two sets of 45° elbows offsets within these vertical
installations. From 0 to a maximum of 8’ (2.4 m) of
vent pipe can be used between elbows. (Fig. 22)

7DVCS must be used to support offsets. (Fig. 22)
This application will require that you first determine
the roof pitch and use the appropriate starter kit.
(Refer to Venting Components List)

CFM140

Typical vertical through-the-roof application

2/01 sta;

rev. 0602 rjs

Max.

8’

(2.4 m)

45°

Max.

8’

(2.4 m)

45°

Max. 40’

(12 m)

Typical Straight-up Installation

Typical
Ceiling

Support

Application

Typical

Roof Support

Application

CFM140

Fig. 22 Vertical through-the-roof installation.

CFM190

TTR Ternim. 2'

1/25/02 sta

rev. 0602 rjs

2’

(610 mm)

Minimum

CFM190

Fig. 23 Proper vent height.

Vertical Through-the-Roof Installation

1. Locate your fireplace.
2. Plumb to center of the 4” (102 mm) flue collar from

ceiling above and mark position.

3. Cut opening equal to 9³⁄₈” x 9³⁄₈” (240 x 240 mm).
4. Proceed to plumb for additional openings through

the roof. In all cases, the opening must provide a
minimum of 1” (25 mm) clearance to the vent pipe,
i.e., the hole must be at least 9³⁄₈” x 9³⁄₈” (240 x 240
mm).

5. Place fireplace into position.
6. Place firestop(s) #7DVFS or Attic Insulation Shield

#7DVAIS into position and secure. (Fig. 24)