the dealer should

complete the following

assembly before the

customer receives

the cutter.

Step 6. attach the driveline to the output shaft of the cutter (1)

and to the PtO of the tractor.

Figure 3

Step 5. Before attaching to tractor, fill gearbox with 90 weight gear oil.

Remove top plug (1) to fill gear box. Remove 1/4" overflow plug (2).

When the oil level reaches the overflow plug, the gear box is full.

Figure 2

(Note: Failure to remove 1/4” overflow plug may cause overfilling that could

cause damage to the gearbox, i.e., seals.)

Figure 4

Figure 2

1

2

Figure 3

Step 7. cutting Height adjustment

to adjust cutting height up or down, remove bolts from tailwheel

adjustment bracket and move to preferred cutting height. Insert bolts,

lockwashers, nuts and tighten. Figure 4

aSSeMBly Section

1

Step 1 - Bolt the a-frame

(strut risers)(1) to the outside of

the top angle(2) using bolts(3), lock-

washers (4), and nuts (5). Do nuts tighten

until assembly is complete. Bolt lift pin (6)

through a-frame. Figure 1.

Step 2 - Insert bolt (9) through stiff-arm (8), through

outside of top rail (2), assemble with lockwasher (10) and nut (11). Do not tighten until assembly is

complete. Step 3 - Insert top bolt (7) through a-frame (1), through stiff-arm (8), through pivot-flex

(9) with spacer (13) insert in middle of pivot-flex, (other side) through stiff-arm (8), through a-frame

(1), and apply nut (14).

Step 4 - Begin tightening assembly. start with step 2, step 3, and then step 1.