RoughDeck HE AutoLift

.

Figure 2-3. V-Top coil cradle option showing orientation

9. Adjust leveling bolts until radius of block comes in contact with rocker link radius.
10. Jack the weigh module and remove setting blocks.
11. Slowly lower the weigh module until it rests on the load cell links.

Note

Note

After the weigh module is lowered into final position, check each load cell mount assembly to ensure that the
link is plumb and that there is no binding or misalignment.

12. Use an industrial hammer drill to drill a 3/4" hole into the concrete at least 6" deep on one side of the

mount frame.

13. Drill a second anchor bolt hole on the opposite side of the mount frame.
14. Each mount requires two anchor bolts to prevent longitudinal motion of the baseplate. Anchor bolts (7" x

3/4") with expansion heads are supplied with the scale.

15. Insert bolts into holes drilled in foundation.
16. Install one washer and one nut on each anchor bolt. Place a driver pipe on top of the anchor bolt and use the

long punch to seat anchor bolts against baseplate.

Do not apply excessive force to the anchor bolts-- bending of the baseplate could occur.

When installing anchor bolts, make sure that there is adequate bolt length to extend into the concrete
foundation.

17. Attach one end of the ground strap to the upper block.
18. Insert a bolt through the wire terminal on the loose end and thread the bolt into the hole on the baseplate.

Tighten the bolt securely with a wrench.

19. Pour 9000 PSI, non-shrinking, epoxy or cement grout under and around the baseplate. A funnel with a

long tube can be used to pour grout under and around the baseplate while working from above the access

hole.

20. Grout should be allowed to set for at least 24 hours before removing the wooden forms.
21. After grout has hardened, tighten anchor bolt nuts.