4.0 Installation

4.1 General Guidelines

The mounts are normally shipped from the factory fully assembled with the load
cells fitted and the mounting screws torqued to the correct values. If the load cells
are removed from the base plate for any reason, they should be reassembled using
the procedure in Section 5.2 and the torque values listed in the following table.

All bolts must be at least grade 5.

The mounts are also shipped with the jack nut tightened down so that the top plate
is lifted clear of the load cell. This is done to protect the load cell in shipping. See
Figure 12 below.

Shipping and Maintenance Position

Weighing Position

Figure 12 Shipping Positions

Each of the three types of Paramounts has identical base and top plate hole loca-
tions for a given capacity. The holes in the top plate are symmetrical around the
loading point permitting rotation of the complete mount for the best line up with
other tank mounts. This also optimizes accessibility to load cell mounting screws
for load cell replacement. Figure 13 on the following page illustrates a preferred
orientation to assure easy access to load cell mounting bolts.

Load Cell Capacity

Bolt

Torque (in ft-lbs)

2.3KN (520lbs)

1/2-13

50

5KN (1,125lbs)

1/2-13

65

10KN (2,250lb)

1/2-13

65

23KN (5,200lb)

1/2-13

65

50KN (11,250lb)

3/4-10

295

100KN (22,500lb)

1-8

515