2 aerco bst quick start chart – AERCO BMK 6000 Dual Fuel User Manual

Page 142

Advertising
background image

Benchmark 6000 DF Installation, Operation & Maintenance Manual

CHAPTER 10 – BOILER SEQUENCING TECHNOLOGY

Page 142 of 219

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

OMM-0096_0B

03/21/2014

Ph.: 800-526-0288

GF-141

10.2 AERCO BST QUICK START CHART

Select the single option that suites your installation and then complete the instructions in the
corresponding sub-sections of section 10.3 BST Implementation Instructions.

Constant Setpoint (choose option 1 or 2)

Option 1 – Direct Wired Header

Complete section 10.3.1

OR

Option 2 – Modbus Header

Complete section 10.3.2


Outdoor Reset (choose option 3 or 4)

Option 3 – Direct Wired Header AND Direct Wired Outdoor Air

Complete section 10.3.3

OR

Option 4 – Modbus Header AND Modbus Outdoor Air

Complete section 10.3.4


Remote Setpoint (choose option 5 through 8)

Option 5 – 4-20ma Drive AND Direct Wired Header

Complete section 10.3.5

OR

Option 6 – Modbus Drive AND Direct Wired Header

Complete section 10.3.6

OR

Option 7 – 4-20ma Drive AND Modbus Header

Complete section 10.3.7

OR

Option 8 – Modbus Drive AND Modbus Header

Complete section 10.3.8