6 Setup

Some virtual terminals require an unlock code to allow the UC5 Spray Height Control system
to operate. If the display prompts for an unlock code, contact NORAC.
There are two methods to setup the UC5 system. The recommended way is to use the
Automatic Setup as shown in Section 6.1. The alternative method is to use Manual Setup,
which is intended for expert users and troubleshooting.

6.1 Automatic System Setup

Unfold the sprayer in a location that is relatively level and where the sensors are over bare soil

or gravel. Do not conduct the Automatic Setup or Retune procedures over standing crop or
weeds/grass. Also, avoid concrete or asphalt surfaces.
Ensure the boom roll suspension system is functioning properly and smoothly. Friction on
wear surfaces can be relieved using lubricants (grease, etc) or adjustment. Properly tuned
suspension systems will optimize UC5 performance.
For best results, the hydraulic system should be under a normal load and at a normal working
temperature.

 Start the solution pump and run the sprayer’s engine at a normal working RPM for the

entire setup.

 Cycle all boom sections up and down manually for five minutes to warm the oil.
 For pull-type sprayers, ensure any hydraulic flow controls are adjusted for normal field

operation.

 Changing the hydraulic flow controls after or during the Automatic Setup will affect the

UC5 performance.


Important

All boom sections will move during the Automatic Setup.
People and equipment must be clear of sprayer boom.
Ensure the booms have sufficient range to lift fully and are clear of any power

lines.