STEP 1: Carefully unpack toilet and place it in the position intended. Center the toilet in the

selected position and assure that adequate clearance is available for opening the seat and lid.

Check the front and sides of the toilet to insure that it will set flat against the floor. Determine the

best location for the flush switch panel. It is recommended that it be near the toilet but not hidden

by the toilet lid in the “up” position. Avoid a location susceptible to direct water spray.
STEP 2: Mark the floor at the rear corners and the front center of the ceramic bowl. Remove the

ceramic bowl and set aside (figs. 1, 2).
STEP 3: Measure the distance between the rear corner marks on the floor and divide by 2 to find

the centerline. Using a carpenter’s square, draw a centerline on the floor that intersects the mark

for the front center of the bowl (fig. 3).

STEP 4: Choose an inlet configuration for the electrical wiring and water line hole location: (a)

through the rear wall, or (b) through the floor.
STEP 5: For electrical cables/wiring and water line installations

through the rear wall, measure

up a minimum of 1 inch (25 mm) and 2 inches (51mm) to the right of the centerline (fig. 4) for the

electrical cables, and 2 inches (51 mm) to the right of the centerline for the water line. Mark the

hole locations.

Toilet Requirements:
• 2 GPM (7.6 lpm) or larger water pump.
• 1/2-inch (12.7 mm) water line terminating in a 1/2-inch female NPT fitting (to connect to toilet

water supply hose).

• 12 VDC or 24 VDC through a fuse or circuit breaker of sufficient size to protect wiring. Circuit

board fuse resets by turning power off and on. Refer to installation codes for proper wire sizes.

VacuFlush

®

4809 ToileT iNsTallaTioN GuiDe

Fig. 1

Fig. 2

Fig. 3

These locations are for the water and electrical

supply line holes in through-the-wall installations.

wall

FlooR

toilet

centerline

water line

location

1 in.

(25 mm)

2 in.

(51 mm)

Fig. 4

STEP 6: Align the 4809 toilet mounting template along the centerline mark with the front edge of

the template flush with the mark for the front edge of the toilet bowl (fig. 5). Tape the template to

the floor.
STEP 7: Using a center punch, mark the center locations for the discharge flange hole, mounting

bracket holes (fig. 6), the four corners of each mounting bracket, and the center of the water line

and electrical wiring holes (if routing these through the floor). Remove the template from the floor.

Fig. 5

Fig. 6

Below-Floor installation

above-Floor installation

iMPoRTaNT: The preferred floor flange installation method is to mount the flange directly on the

finished floor. However, if the bottom of floor flange and bottom of ceramic toilet must be mounted

at different heights, the floor flange must be mounted within 3/8-inch (10 mm) of the bottom of the

toilet (see illustrations below) or leakage will result.

STEP 8: Cut out the 4-3/4-inch (120 mm) diameter discharge flange hole. Drill the two 3/16-inch

(5 mm) holes mounting bracket fastener holes. Where required (floor or wall), drill the 1-inch

(25 mm) diameter water line hole and 1 3/4-inch (44 mm) electrical wiring hole.
STEP 9: VERTICAL DISCHARGE HOSE – Using PVC primer and solvent cement, attach the hose

adapter directly into the discharge flange outlet. Allow to cure before handling. HORIZONTAL

DISCHARGE HOSE – Using PVC primer and solvent cement, attach the elbow directly to the

discharge flange outlet. Then attach the hose adapter into the elbow (fig. 7). Allow to cure before

handling.
STEP 10: Insert the discharge flange into the hole with the elbow pointing in the direction of the

discharge plumbing. Mark the floor through the eight countersunk mounting holes. Remove the

flange and drill the eight pilot holes with an 11/64-inch (4 mm) drill bit.

Fig. 7

STEP 11: Route the vacuum hose from the vacuum generator or vacuum tank up through the

discharge flange hole. Lubricate the inside of the hose with liquid dishwashing soap and install the

hose onto the adapter. Secure the connection with two stainless steel hose clamps (fig. 8).
STEP 12: Insert four T-bolts into the discharge flange from the underside.
STEP 13: Insert the discharge flange and connected hose or pipe into the discharge hole and

secure to the floor with the eight #12x1-1/2-inch flat head screws provided (fig. 9).

STEP 14: Install the flange gasket over the T-bolts (fig. 10).
STEP 15: Install floor flange adapter with words “THIS SIDE UP” facing up. Tighten adapter to

floor flange using four flat washers and hex nuts. Tighten in criss-cross pattern (fig. 11).

STEP 16: Route 1/2-inch (13 mm) diameter water line from the fresh water source through the

1-inch (25 mm) hole in the wall or floor and attach a 1/2-inch female NPT fitting (fig. 12).

Note: A shut-off valve should be placed in the water line to the toilet for maintenance or repair.
STEP 17: Several flush switch options can be ordered from Dometic. Instructions for installing the

basic Dometic flush switch are on the next page.
Two other available types fit either VIMAR or GEWISS panels and housings. The VIMAR and

GEWISS panels use one switch for both “Flush” and “Add Water” functions. Instructions are

included with each flush switch assembly.
Install flush switch in desired location and route electrical cables/wiring through the 1 3/4-inch

(44 mm) hole to the toilet. Leave 12 inches (305 mm) of cable to connect to the toilet (fig. 13).

(The cable supplied with the basic Dometic flush switch will have a Deutsch connector.)

Fig. 8

Fig. 9

Fig. 10

Fig. 11

Fig. 12

Fig. 13

Fig. 14

Fig. 15

Fig. 17

Fig. 16

SEE NEXT PAGE FOR DOMETIC WALL-MOUNTED FLUSH SWITCH INSTALLATION

AND TOILET SYSTEM WIRING DIAGRAM.

STEP 18: WITH POWER OFF, route electrical cables/wiring from vacuum generator and power

source through 1 3/4-inch (44 mm) hole (fig. 13). Leave at least 12 inches (305 mm) of wire above

the floor or through the wall to connect to toilet. (See wiring diagrams on next page. If Deutsch

connectors (shown) are not being used, refer to wiring diagram to make proper connections in

Step 20).

STEP 19: Secure the toilet mounting brackets to

the floor using the #14 x 2 ½-inch (65 mm) hex

washer head screws and support plates

provided. Be sure to mount the brackets as

shown on the template (fig. 14).
STEP 20: Set the toilet in front of the discharge

adapter. Connect the flexible water hose to the

1/2-inch female NPT fitting on the inlet water

line. Connect the cable/wiring from flush switch

to the toilet’s flush switch-status panel cable/

wiring. Connect the cable/wiring from vacuum

generator and power source to the toilet’s

vacuum generator-power source cables/wiring.
IMPORTANT – DO NOT ATTEMPT TO SLIDE THE TOILET OVER THE DISCHARGE ADAPTER.

THE TOILET MUST BE SET DOWN INTO THE ADAPTER TO PREVENT POSSIBLE DAMAGE.
STEP 21: Lubricate the O-ring around the bottom of the toilet base with liquid soap or silicone

spray or grease. Pick up the toilet and insert plastic base assembly into discharge adapter. Make

sure mounting brackets on floor do not interfere with bottom of ceramic toilet (fig. 15). If the

mounting brackets interfere, loosen mounting screws and adjust bracket location accordingly.
STEP 22: Insert the two plastic flange bushings

into the toilet mounting holes and secure the

toilet to the mounting brackets with the two flat

head wood screws provided (fig. 16). Be sure

to drive fasteners into mounting brackets at a

downward angle.
STEP 23: Press the decorative screw covers

over the flange bushings (fig. 17).

2 in.

(51 mm)

electric cable

location