CONTENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .PAGE

Basic Guidelines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1

Application (Flex-L Vent Terminal)

Direct Vent Applications . . . . . . . . . . . . . . . . . . . . . .2 & 3

Installing the joint assembly . . . . . . . . . . . . . . . . . . . . . . . .4

Outside Terminal

Installing the outside terminal . . . . . . . . . . . . . . . . . . . . .5

Connections to the outside terminal . . . . . . . . . . . . . . . .6

Connections to appliance . . . . . . . . . . . . . . . . . . . . . . . . . .7

Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8

Vent system part numbers . . . . . . . . . . . . . . . . . . . . . . . . .8

Alternate Field Controls Vent Terminal . . . . . . . . . . . . . .8-14

Slant/Fin TR SERIES, models TRDV are approved for installa-

tion as a direct vent system. The following basic guidelines

should be observed according to the venting system in use.

In addition, it is strongly recommended that the applicable

precautions for Natural Draft Applications be used.

In addition to all the pertinent information regarding Natural
Draft Applications whenever a Mechanical Draft Application is
used it should be installed using the following instructions and
Figures 2 and 3 as reference.

The terminating vent hood, and the inlet air hood are on
the same wall surface. and are on the wall opposite from
the prevailing wind wall, if possible.

All of the air for combustion to the burner is supplied
directly from the outside of the building or structure.

Not less than 12 in. above the total accumulated
snow and level grade.

Not less than 4 ft. horizontally or below any
window, and door or air inlet and also not less than
1 ft. above any of these openings.

Not less than 3 ft. above a powered air inlet
device that is within 10 ft.

Not less than 2 ft. from any other building.

At least 3 ft. from any inside corner of a building

At least 1 ft. from any roof soffit or ridge vent.

At least 7 ft. above any public walkway.

All of the vent construction consists of suitable materials,
and terminates at an approved stainless steel hood.

All of the vent piping must be sealed from air leaks.

The vent pipe bend radius is 12 in.

Brace metal strapping every 36 in. to support
vent pipe and prevent it from sagging.

Follow the national codes for the installation of oil burning
equipment in USA-NFPA 31, in Canada CAN/CSA - B139
and local regulations.

FIGURE 1: Slant/Fin model TRDV oil boiler with
vent kit

DIRECT VENT OIL-FIRED WATER BOILER

VENTING INSTALLATION INSTRUCTIONS

INTREPID

TRDV Series

PUBLICATION NO. TRDV40-V

Printed in U.S.A. 613

Part No. 43-2770

Installation Considerations