HEATING A COOLING

38QH

Heat Pumps — Outdoor Section

Installation and Start-Up Instructions

SAFETY CONSIDERATIONS

Installing and servicing air conditioning equipment

can be hazardous due to system pressure and electrical

components. Only trained and qualified service personnel
should install or service air conditioning equipment.

Untrained personnel can perform basic maintenance,

such as cleaning and replacing filters. All other operations
should be performed by trained service personnel. When
working on air conditioning equipment, observe pre­
cautions in literature and on tags and labels attached

to unit.

Follow all safety codes. Wear safety glasses and

work gloves. Use quenching cloth for brazing opera­
tions. Have fire extinguisher available. Read these
instructions thoroughly. Consult local building codes
and National Electrical Code (NEC) for special installa­
tion requirements.

A WARNING

Before installing or servicing unit, turn off main

power to system. There may be more than one dis­
connect switch. Turn off accessory heater power if
applicable. Electrical shock can cause personal
injury.

DISCHARGE
GRILLE

CONTROL

BOX I 5-5/(

1-1/8" DIAM
HOLE WITH
1-3/8"

CONCENTRIC

KNOCKOUT '

FOR POWER

WIRING

(OPP SIDE)

LIQUID LINE

SERVICE PORT
AT SERVICE^

VALVE(CLG

CYCLE)

SUCTION
SERVICE POR

AT SERVICE
VALVE(CLG

CYCLE)

SUCTION
SERVICE PORT

(HIDDEN)

r-6" AIRFLOW AND

SERVICE CLEARANCE
ON 3 SIDES — 12" ON

REMAINING SIDE

INSTALLATION

Step 1 — Check Equipment and Jobsite —

Install on a solid, level mounting pad. It is recommended

that unit be attached to pad using tiedown bolts. Fasten
unit to pad using holes provided in unit mounting feet.
See Fig. 1.

When installing, allow sufficient space for airflow

clearance, wiring, refrigerant piping and servicing. Main­

tain a minimum of 4 ft clearance from obstructions above
and 18 in. on 3 sides of unit (12 in. on fourth side). Main­
tain a distance of 24 in. between heat pumps. Position so
water or ice from roof or eaves cannot fall directly on unit.

Step 2 — Replace AccuRater™ Refrigerant
Control Piston in the indoor coil, if required, before

conneeting refrigerant lines. See AccuRater Selection

Charts, Table 2.

Step 3 — Make Piping Connections — Outdoor
units may be connected to indoor sections using Carrier
accessory tubing package (refer to Service data) or field-
supplied tubing of refrigerant grade, correct size and

condition (Table 1). For tubing requirements beyond
50 ft, obtain information from local Carrier distributor.

Outdoor units connected to Carrier-approved indoor

units contain correct system refrigerant charge for opera­

tion with indoor unit of the same size when connected by

25 ft of field-supplied or Carrier aceessory tubing. Check

refrigerant charge for maximum efficiency (refer to

Table 5 and Service data).

NOTE Mounting pad may be square or circular

MODEL 38QH

015,018

024-048

060

DIAMETERS (ft-in.)

1-9Y2

2-5'/4

3-3

SQUARES (Minimum)

(in.)

23

30

40

TIEDOWN BOLT C

o-ey.

0- 9'/2

1-1'=/i6

LOCATION (tt-in.) D

1-4

1-10V2

2-7

E

0-9'/4

1-1

1-5ye

Fig. 1 — Dimensions, Connections and

Mounting Pad (Refer to Table 1)

Manufacturer reserves Ihe right to discontinue, or change at any time, specifications or designs without notice and without incurring obiigations.

Bookll |4

PC 101

Catalog No 533-808

Printed inUS A

Form38QH-2SI

Pg 1

7-85