2. Bolt suspension clips (supplied), one near each

corner of fan section and one near each end of
coil section. Tighten bolts (supplied) securely.

3. Lift unit into position.
4. Pass threaded hanger rod (field-supplied) thru

each suspension clip.

5. Fasten with nuts (field-supplied).

VERTICAL ARRANGEMENT

1. Bolt legs (accessory) to inlet side of coil

section, using 5/8 in. - 11 captive nuts (located
on inward flanges of coil section) and bolts
(supplied). Tighten securely.

2. Rotate motor end bells 90 degrees so drain

holes are at bottom. Rotating end bells must be
performed by an authorized vendor’s motor
repair shop.

Refrigerant Piping

GENERAL — All field leak and pressure testing
should be in accordance with local code require­
ments. If no local code exists, use American

Standard Safety Code for Mechanical Refrigeration
(A.S.A. B9.1).

Eor leak testing procedures, refer to the Carrier

Standard Service Techniques Manual, Chapter 1,
Section 1-6.

Refrigerant line sizing depends on length of

lines between various sections of the refrigerant

system. Consider the amount of liquid lift and
drop in the system as well as proper compressor oil
return. Consult Carrier System Design Manual, Part
3, for proper piping sizes and design.

Liquid and hot gas connections for any one

split are same size so coil may be reversed for
opposite-hand connection, but must be piped for
counter flow in any case.

LIQUID SHUT-OEF VALVE AND SIGHT GLASS
— Shut-off valve is not supplied with units. It is
strongly recommended that a full line size liquid
shut-off valve be field supplied near condenser to
allow for servicing parts of the refrigerant circuit.
A field-supplied, moisture-indicating sight glass is
recommended for use in charging and servicing the
system. Refer to Fig. 2 for location.

The American Standard Safety Code for

Mechanical Refrigeration (A.S.A. B9.1, 1964, para­
graph 12.1) states as follows: “Every refrigerating
system shall be protected by a pressure relief
device unless so constructed that the pressures due
to fire conditions will be safely relieved by some
part of the system.” Since the 09FA units have no
pressure relief device, it should be field supplied
and installed. When the split coil is used with
multiple systems, each system must have a pressure
relief.

COIL CONNECTIONS - Refer to Eig. 2, 3. Make
connections.