2. SITING

The temperature measurements used in

meteorology are intended to represent general

conditions over as large an area around the

measuring point as possible. They are usually

taken at a height of 1.25 m above ground level.
To achieve the most representative local

conditions, the measurement station should be

sited in an unobstructed area open to the sun

and wind. Sites sheltered by trees or buildings,

in hollows or on the sides of hills are not

recommended, neither are sites on buildings,

as none of these locations will give

representative measurements.
The Casella Advanced Instrument Shelter is

designed to meet these conditions. It is

supplied with a 1.4 m high stand that must be

partially buried in the ground to give a

thermometer height of 1.25 m. Mounting the

stand on buried concrete blocks will offer

additional stability.
When on-line connection or telemetry is

required, a suitable power supply must be

provided.
The U.K. Met Office (Meteorological Office)

recommends that the instrument shelter be

installed over closely mown grass. Refer to the

Met Office leaflets:

Manual weather measurements,

Automatic weather measurements,

Making weather observations,

for further guidance.

3. SCHEDULE OF PARTS

The Advanced Instrument Shelter consists of

the following parts.

M113011

Screen, with two drop-

down doors, supplied

ready assembled and

painted,

M131026A

Stand, supplied as a

pre-fabricated kit.

HB3283

Installation Guide

The Stand Kit has 12 components, plus

fastenings.

4

Uprights (5 cm galvanised

angle iron)

2

Lower cross members

(5 cm galvanised angle iron)

2

Upper cross members

(5 cm galvanised angle iron)

4

Diagonal cross braces

(4 cm galvanised angle iron)

4

M10 x 60 mm bolts for

attaching the screen

18

M10 x 30 mm bolts for

assembling the stand

22

M10 nuts

22

M10 lock washers

When the equipment is delivered, please

check that all items on this schedule have

been supplied.
The assembled stand and screen are shown in

the figure.

4. INSTALLATION

1 Check that all of the components listed in

the schedule of parts have been delivered.

2. Following the figure, assemble the stand

using the 30 mm bolts.
Leave the fastenings loose enough for final

adjustment.

3. Stand the stand upright on its feet.
4. If the stand is to be attached to concrete

blocks, attach it now.
Again, leave the fastenings loose enough for

final adjustment.

5. Carefully fit the screen on to the top of the

stand using the 60 mm bolts.

6. Tighten all fastenings.
7. Dig a suitable hole at the measurement site

to accommodate the feet of the stand.
The shelter must be oriented so that the

door which opens to give access to the

thermometer(s) is on the north side.

This will ensure that the measurements are

not subjected to sudden high temperatures

from direct sunlight when the door is

opened to inspect the instruments.

8. Stand the complete assembly in the hole.
9. Adjust the height so that the thermometer(s)

can be installed at 1.25 m above normal

ground level.

10.Make sure the assembly is upright, with the

floor of the screen horizontal, so that rain

can drain from the sloping roof.

11.Fill the hole, packing the soil down firmly,

and leave space for a layer of turf at the top.
Bed the feet in concrete if required.

12.Lay turf to cover the hole.
13.Install the instrumentation.
As the stand is manufactured from hot dipped

galvanised iron, no painting or other weather

protection should be required.

Side 3

ADVANCED INSTRUMENT SHELTER

User Instructions

Side 2

ADVANCED INSTRUMENT SHELTER

User Instructions

01041

5. SITE MAINTENANCE

Make sure the enclosure is kept clean and free

from staining, algae etc. Wipe frame and slats

with mild detergent, possibly with a small

quantity of disinfectant to discourage algae

growth.

Keep the grass properly mown and free from

weeds to maintain the “1.25 m height above

ground” requirement.

6. TECHNICAL INFORMATION

Screen Specification

Construction:

Polyester powder coat with chromatic

pre-treatment over aluminium frame for UV

and salt spray resistance,

Injection moulded louvres with enhanced

UV inhibitor,

Stainless steel fittings,

Door hinges with stainless steel pins.

The screen is supplied pre-assembled.
Dimensions: Width x Height x Depth

Internal 492 mm 411 mm 313 mm

External 670 mm 576 mm 500 mm
Weight: 26 kg

Stand Specification

Construction:

5 cm and 4 cm hot dipped galvanised angle

iron with M10 nut and bolt fastenings.

The stand is supplied as a pre-fabricated kit for

assembly in the field.

M10 spanners will be required.
Dimensions: Width x Height x Depth

Overall

664 mm 1400 mm 521 mm

Weight: 31 kg