Installation – Flowserve NRGS 11-2 User Manual

Page 12

Advertising
background image

2

Attention

The seating surfaces of the threads or flange provided on the vessel or boiler standpipe

must be accurately machined.

Fig. 3

Do not bend electrode tip when mounting.

Do not lag electrode body.

Note

For the approval of the boiler standpipe with connecting flange the relevant local and

national regulations must be considered.

See four examples of installation on page 3.

Tools

Open-end spanner 4 mm A. F.

Bolt cutter

Hacksaw

Flat file, medium cut

Installation

NRGS 11-2, NRGS 16-2

. Determine required measuring lengths of electrode tips and enter data in

table 1, Fig. 2.

2. Cut electrode tips

1 , 2 , 3 and 4 accordingly.

The electrode tips

1 and 2 (low level limiter) must have the same length.

3. Deburr faces of electrode tips.
4. Strip off 50 mm of PTFE insulation from the ends of electrode tips.
5. Check seating surfaces of threads or flange provided on vessel or boiler standpipe.

Fig. 3

6. Place joint ring

C onto seating surface B of electrode Fig. 2. Use only joint ring

(of stainless steel .430) D 33 x 39 to DIN 7603 supplied with electrode.
7. Apply a light smear of silicone grease (e. g. DOW Corning  Compound) to electrode thread

D.

8. Screw level electrode into threads or flange provided on vessel or boiler standpipe and tighten

with a 4 mm open-end spanner. The torque required is 40 Nm when cold.

Table 1

Enter data here!

Function

Function

Electrode tip

Length [mm]

Low-level alarm



Low-level alarm

2

e. g. Pump ON

3

e. g. Pump OFF

4

Advertising