Installation

– continued –

Mounting electrode

– continued –

Observe TÜV (German Technical Supervisory Association) regulations when using the level
electrode in steam boilers or (pressurised) hot water plants.

For the approval of the boiler standpipe the relevant local and national regulations must
be observed.

Several examples of installation are given on page 12.

The angle of installation of the electrode must not exceed 45° and the length of the elec-
trode rod is limited to 500mm!

If installed outdoors the level electrode must be equipped with a GESTRA weather pro-
tection cover.

Tools

Open-end spanner 22 mm A. F.

Bolt cutter or metal cutting saw

Flat file, medium cut