Installation – Flowserve UBK 46 User Manual

Page 13

Advertising
background image

13

1. Observe position of installation.

2. Observe flow direction. The flow direction arrow is located on the trap body.

3. Leave at least 70 mm free space around the equipment for subsequent disassembly of the cover C

C

C

C

C.

4. Remove plastic plugs. They are only used for transit protection.

5. Remove regulator as described under “Maintenance”.

6. Clean socket-weld ends.

7. Arc-weld trap only manually (welding process 111 and 141 complying to ISO 4063 or equivalent

standard).

1. Observe position of installation.

2. Observe flow direction. The flow direction arrow is located on the trap body.

3. Leave at least 70 mm free space around the equipment for subsequent disassembly of the cover C.

4. Remove plastic plugs. They are only used for transit protection.

5. Clean internal threads.

6. Install steam trap.

1. Observe position of installation.

2. Observe flow direction. The flow direction arrow is located on the trap body.

3. Leave at least 70 mm free space around the equipment for subsequent disassembly of the cover C.

4. Remove plastic plugs. They are only used for transit protection.

5. Clean gasket surfaces of the two flanges.

6. Install steam trap.

Installation

UBK 46

The UBK 46 can be installed in any position. When installed horizontally the cover must be on top.

Design with flanged ends

Design with screwed sockets

Design with socket-weld ends

Design with butt-weld ends

1. Observe position of installation.

2. Observe flow direction. The flow direction arrow is located on the trap body.

3. Leave at least 70 mm free space around the equipment for subsequent disassembly of the cover C

C

C

C

C.

4. Remove plastic plugs. They are only used for transit protection.

5. Clean butt-weld ends.

6. Arc-weld trap manually (welding process 111 and 141 complying to ISO 4063 or equivalent

standard) or use gas-welding process 3 in accordance with ISO 4063.