Legrand DSBEA User Manual

Installation instructions

Advertising
background image

Legrand Delta Strut Solar Systems

have passed electrical/bonding

testing per UL 2703. The following

paragraph states the scope of the

UL standards:

These requirements cover rack

mounting systems and clamping devices

for flat-plate photovoltaic modules and

panels that comply with the standard

for Flat-Plate Photovoltaic Modules

and Panels, UL 1703, intended for

installation on or integral with buildings,

or to be freestanding (i.e., not attached

to buildings), in accordance with the

National Electrical Code, ANSI/NFPA 70

and Model Building Codes.

Installation Instructions:

1. Snap chalk lines for each DS

(Delta Strut) stringer row.

Rows should be located at even

intervals allowing roughly 1/4 of

the total PV length to overhang

the top and bottom stringer

(Allow 1/8” minimum between

panel rows for expansion).

2. Install DS-S5 clamps to roof

seams as required. Install on

roof seams (not exceeding

maximum span of 60” or roof

loading requirements).

3. Attach DSBRSW washer to

DS-S5 seam clamps using

bolt provided. Then attach DS

stringers to DSBRSW/DS-S5

assembly using DSPCC clamp

and self-threading screws

(sold separately). [Figure A]

4. Splice sections of DS together

using a DSSA splice kit (install

splices on both inside corners

of DS for a single splice). Torque

nuts to 6-8 ft/lbs. [Figure B]

5. Pull string cabling into DS

stringer row.

6. Position first PV panel at the

beginning of first run, checking

for position and square, then

attach to DS using DSEHDC

(End Bolt/Clamp). Torque nuts

to 6-8 ft/lbs.

7. Connect PV cables to stringer

cables and secure cabling to

DS. Be aware that cabling is live

at this point.

8. Add next PV panel in run. Use

DSMHDC (Middle Bolt/Clamp -

Patent Pending) in areas where

two panels adjoin, ending each

row by utilizing a DSEHDC

(End Bolt/Clamp). Torque nuts

to 6-8 ft/lbs. [Figure C]

9. Each solar row to be connected

to Earth as specified in NEC

using proper sized ground

conductor and UL Listed

Split-bolt lug connected to

Delta Strut. [Figure D]

Solar panels supported by Delta Strut

on Metal Raised Seam Roof

For optimal holding strength,

screw tension should be 160

to 180 inch pounds on 22

ga. steel and 130 to 150 inch

pounds for all other metals

and thinner gauges of steel.

DS-S5

DSBRSW

DSPCC

DSMHDC is spring-loaded and

stays in position while panels

are positioned.

DSMHDC

Use two DSSA to splice any two

sections of Delta Strut tray.

DSSA

Use GNDSB split-bolt lug

grounding connector to

properly ground each solar

support row.

GNDSB

FIGURE A

FIGURE B

FIGURE C

FIGURE D

C

A