Installation, Top vent venting runs – Montigo ME34-DV2 User Manual

Page 6

Advertising
background image

Page 

Part No. XG0105B

ME34-DV-2 Homefire

Installation

Top Vent Venting Runs

For the ME34-DV-2 Top Vent, there are two types of installations: A)

Through-The-Wall Installations and B) Vertical (Through-The-Roof)
Installations.

A) Through-The-Wall Installations

Before you install any venting, you must determine whether the
venting run will be acceptable. Unacceptable venting can affect the
fireplace's combustion.
The Venting Graph
Measure the vertical height from the fireplace hearth to the centre of
the termination and the horizontal run from the from the fireplace flue
collar to the wall flange of the termination. Plot on the Venting Graph
(Fig. 7) with an 'X'.
If the 'X' falls on or above the top boundary of the shaded area, the
installation is acceptable.
Example A: (Acceptable Installation)

If the vertical dimension from the hearth is 84" and the
horizontal run to the wall flange of the vent termination
is 36", this would be an acceptable installation.

Example B: (Acceptable Installation)

If the vertical dimension from the hearth is 90" and the
horizontal run to the wall flange of the vent termination
is 126", this would be an acceptable installation.

Example C: (Unacceptable Installation)

If the vertical dimension from the floor of the fireplace is
78" and the horizontal run to the wall flange of the vent
termination is 108", this would noT be an accept-
able installation.

0 12 24 36 48 60 72 84 96 108

132

120

144 156 168 180

Horizontal Run (in.)

Hearth

0

12

24

36

48

60

72

84

96

108

Figure 8.

Heat Shield. Install by sliding over the vent pipe where it

passes through combustible construction.

Heat Shields

Due to high flue temperatures, heat shields
are required on all 34 Series Modular Direct
Vent installations (except those with vertical
terminations) at the point where the venting
connects to the termination. With the heat
shield, vent clearances can be maintained
at 1".

Figure 7.

ME34-DV-2 Top Vent Venting Graph

Top Vent

Available Top Vent Components

The following venting components are available for the ME34-DV-2
Top Vent:

A - Termination

MTO-3 (3" length)

MTO-3F (3" length)

B - Stucco Kits

MSR (stucco frame)

MOSR (stucco can)

BSR (brick can)

D - Flex sections

MFL-1 (12" section)

MFL-18 (18" section)

MFL-2 (24" section)

MFL-3 (36" section)

MFL-4 (48" section)

E - Solid sections

EXT-18 (18" f/f section)

MEXT-1 (12" m/f section)

MEXT-2 (24" m/f section)

MEXT-3 (36" m/f section)

MEXT-4 (48" m/f section)

F - Elbows

MEL-90M (m/m 90° elbow)

MEL-90F (f/f 90° elbow)

MEL-90FM (f/m 90° elbow)

EEL-45 (f/m 45° elbow)

NOTES:

All dimension lengths for vertical or horizontal runs are

measured from center of the vent pipe.

Venting runs

must fall within the limits set by the vent-

ing graph (see Figure 7).

Advertising