INSTALLATION PROCEDURES

6

T-802 . . .

Installation

1. T-802 is installed just as T-80 and T-85.

2. Mix the two-part compound.

3. Install with a hand trowel.

4. Air curing will occur as noted on page 1. The T-802 can be

put into service without curing.

Typical Cross Section

EFS-1 . . .

Installation

1. Cut the EFS to desired size.

2. Place the EFS between the surface of the heat source and

the equipment being heated.

3. Mechanically secure the heat source to equipment.

4. No curing is required.

NH Non-hardening . . .

Installation

1. Approximate thickness of compound required is 3 mm

to 6 mm covering the entire contact side surface area of
plate(s). Coverage rates are 6 m

2

per 19 liters for 3 mm

thickness, 3 m

2

per 19 liters for 6 mm thickness.

2. Heat NH heat transfer compound to approximately 95°C

to 120°C before application.

3. For best results, preheat the plate surface(s) to 95°C to

120°C; this will allow the compound to flow more smooth-
ly onto the plate surface(s).

4. Trowel on and spread the hot heat transfer compound

over the plate surface(s) using a mortar trowel. After

spreading the compound over the entire surface, ensure
that sufficient compound is installed to fill the normal air
voids and other irregular surfaces which may exist on the
vessel or plate.

5. No curing is required.

6. Install the plate(s) on the vessel wall.

7. Insulate and weatherproof.

N

NH Non-hardening Compound
Troweled onto a Heater Surface

Typical Cross Section

3 mm to 6 mm

NH Non-hardening

Compound

EFS-1

Heater Plate *

2D

T-802

D

* Such as HeetSheet

®

vessel heating unit.