7.

Apply a liberal amount of RTV sealant to cable.

5.

Cut V-notch in matrix and pull wires from matrix.

6.

Cut and remove remaining center core of matrix.

4.

Skive outside edges of primary insulation and
black matrix.

Power Connection Instructions

1.

Cut and remove heating cable overjacket as
shown.

Do

not cut metallic braid.

2.

Separate braid strands at edge of overjacket and
pull cable through opening in braid.

3.

Twist braid into a pigtail. Trim ends of braid.

15 mm

(6”)

117 mm

(4.6”)

8.

Slide boot onto the end of the cable.

13 mm

(.5”)

INSTALLATION PROCEDURES