Bunk Loadguide for PT1420 - PT1720 Models

ASSEMBLY AND INSTALLATION INSTRUCTIONS

Assembly Instructions

Break the bundles and sort all items. Locate the post load

guide weldments and position one on the rear cross mem-

ber.

Orient the weldment as shown in the diagram. Place two

– 3/8” x 2 7/16” x 4” U-bolts up around the cross member

and into the holes provided in the weldment. Secure with

3/8” flange lock nuts. Do not tighten. Repeat this process

with another post load guide weldment on the front cross

member.

Position the carpeted bunk on the outside of the weldments

just installed as shown in the diagram. Attach the bunk to

both the front and rear weldments using the bolts already

installed in the bunks. Secure to the weldments using 3/8”

lock washers and hex nuts.

Repeat the above process on the other load guide on the

other side of the trailer.

Adjustment

With the pontoon properly centered on the trailer slide the

load guides out until they are within ½” of the inside of the

pontoon tube. Tighten in position. Tighten the bolts attach-

ing the bunks to the weldments. This is a good starting

point for adjusting. They may need to be adjusted differ-

ently depending on the splash guard on the front of the

pontoon tubes. Unload and reload the pontoon to make

sure they are adjusted to best fit your pontoon. They can be

repositioned to best fit your need.

Adjustment is complete.