Jordan Valve Mark V-100 Series Control Valve User Manual

I & m mark v-100 series, Nstallation, Ntroduction

Advertising
background image

I

nstallatIon

The valve body and internal components are made

of specific materials, and are designed for specific

temperature, fluid control, pressure, and pressure drop

conditions. The following listed parts may compromise

the valve if temperature ranges and service drops

have been exceeded; Body, bushings, shaft, and ball

seals.

Operation of these valves outside the specified ap-

plication ranges may cause damage to equipment and

or personal injury.

These valves must not be used outside the specified

condition ranges without contacting your Jordan Valve

sales representative.

Jordan Valve recommends the installation of pressure

control or pressure relieving devices.

Inspect the valves for shipping damage and

foreign debris when uncrating.

Jordan Valve recommends the installation of a stan-

dard three-valve maintenance by-pass system. This

allows for isolation of the valve body without shutting

down the pipeline.

1.

Ensure the pipeline is free of welding slag,

and foreign debris by blowing out

the pipe lines before installation.

2.

When mounting between pipeline flanges,

ensure the two connecting flanges are in

line. Install approved gaskets between

the valve body and the pipeline flanges.

3.

Position the valve on the line so that the

flow direction indicator corresponds to

to the direction of the flow of the pipeline.

If the valve body is being used in a bi-directional

flow application then the flow direction indicator

should correspond to the direction of the highest

flow condition.

4.

When installing flange bolts, use figure No. 4

to obtain necessary clearances.

5.

Tighten the bolts in a crisscross pastern

to ensure all bolts are evenly torqued.

6.

Install the Mark V-100 ball valve horizon

tally in the pipeline with the ball valve

closing downward. The actuator can be

installed in a number of positions; refer to

figure 3 and the actuator instruction manual.

7.

When a manual actuator is used in combination

with a power actuator, it will be necessary to

install a bypass valve on the power actuator

This will allow the operation of the manual

actuator. Following the power actuator

instruction, connect the pressure line to the

actuator.

Note: Grounding the valve shaft is required when the
valve is exposed to hazardous goods or installed for
oxygen use. Without grounding the valve shaft, an
explosive situation may result from the static elec-
tricity from the valve parts.

I

ntroductIon

These instructions apply specifically to the 2 through

12 inch Mark V-100 Ball Series Valve Bodies. This

manual provides maintenance, operation, installation,

and parts ordering information. The valve bodies are

normally equipped with actuators and accessories.

Please refer to the appropriate instruction manuals.

I & M Mark V-100 Series

3170 Wasson Road • Cincinnati, OH 45209
Phone 513.533.5600 • Fax 513.871.0105 (f)
[email protected] • www.jordanvalve.com

Installation & Maintenance Instructions for the

Mark V-100 Series Control Valves

Warning: Jordan Valve Control Valves must only be used, installed and repaired in accordance with these Installa-
tion & Maintenance Instructions. Observe all applicable public and company codes and regulations. In the event
of leakage or other malfunction, call a qualified service person; continued operation may cause system failure or
a general hazard. Before servicing any valve, disconnect, shut off, or bypass all pressurized fluid. Before disassem-
bling a valve, be sure to release all spring tension.

Advertising