2chiller installation, 1 electrical connections, 2 process water connections – HP QuarterHorse Series 0.25 hp Portable Chiller PS-025 User Manual

Page 11

Advertising
background image

PS QuarterHorse Series Chillers

Page 11

2

Chiller Installation

2-1 Electrical Connections

Check serial tag voltage and amperage requirements and make sure your electrical
service conforms. See Figure 2 on Page 10 for total running amps.

;

Electrical connections must comply with all applicable electrical codes.

;

The chiller must be grounded in accordance with NEC Article 250.

;

Voltage must be within 10% of the chiller’s nameplate rating.

2-2 Process Water Connections

;

All external chilled water connections to the process must be of adequate

size.

;

See Figure 4 on Page 14 for sizing recommendations.

;

The largest possible openings and passages should be provided for the flow

of chilled water through platens, dies, molds or other pieces of equipment.

Important!

Keep any pressure drop in external process piping

to an absolute minimum for optimum unit operation.

To Process
Connect the

TO PROCESS

chilled water supply outlet to the process being cooled.

From Process
Connect the

FROM PROCESS

chilled water return inlet to the return from the process

back into the chiller for cooling and recirculation.

;

This chiller model has a strainer on the

FROM PROCESS

return line.

Advertising