Prepare Jobsite

CMW

Prepare Jobsite

Install Fluid Unit

Consider Load Requirements

Installation Tips

Drill holes through trailer cross members to provide adequate connection to trailer structure, not just
deck boards.

Use high-quality, properly-sized mounting hardware.

Jobsite hazards could cause death or serious injury. Use

correct equipment and work methods. Use and maintain proper safety
equipment.

NOTICE:

If jobsite classification is in question or if the possibility of unmarked electric utilities exists, classify
jobsite as electric.

Cutting high voltage cable can cause electrocution. Expose lines by hand before digging.

All vegetation near operator’s station must be removed. Contact with trees, shrubs, or weeds during
electrical strike could result in electrocution.

IMPORTANT: The FM5 unit must be installed on a trailer or truck that meets the following requirements.

All trailer or truck components including axles and tires are in good condition.

Axle loads meet US requirements. In countries other than the US, check local regulations.