Exhaust manifold procedure, Intake manifold procedure, Cylinder head procedure – Generac Power Systems 005213-0 User Manual

Page 16

Advertising
background image

MAINTENANCE PERFORMED BY
AUTHORIZED SERVICE FACILITIES

Before working on the generator, ensure the fol-

lowing:

• The AUTO/OFF/MANUAL switch is in the OFF

position.

• The 15A fuse has been removed from the con-

trol box.

• The 120VAC supply to the battery charger is

switched OFF.

EVERY THREE MONTHS

1. Check

battery

condition.

2. Inspect and test fuel system.
3. Check

transfer

switch.

4. Inspect

exhaust

system.

5. Check engine ignition system.
6. Check

fan

belts.

ONCE EVERY SIX MONTHS

1. Test Engine Safety Devices (low oil pressure, low

coolant level, high coolant temperature).

ONCE ANNUALLY

1. Test engine governor; adjust or repair, if needed.
2. Clean,

inspect

generator.

3. Flush

cooling

system.

FIRST 100 OPERATING HOURS

1. Change engine oil and oil filter. After initial

change, service engine oil and filter at 150 operat-
ing hours or six months, whichever comes first.

2. Retorque

cylinder

head.

3. Retorque intake and exhaust manifold.

EVERY 500 OPERATING HOURS

1. Service

air

cleaner.

2. Check

starter.

3. Check engine DC alternator.

EVERY 800 OPERATING HOURS

1. Retorque

cylinder

head.

2. Retorque intake and exhaust manifold.
3. Check

engine

compression.

4. Check

valve

clearance.

‹

‹

‹

‹

‹

‹

EXHAUST MANIFOLD PROCEDURE

1. If necessary, clean gasket surfaces on exhaust

manifold and cylinder head.

2. Install exhaust manifold and exhaust manifold

gasket.

3. Install

fasteners.

NOTE:

Exhaust manifold fasteners must be tightened in
two stages.

4. Tighten fasteners to 20-30 N-m (15-22 lb-ft) dur-

ing the first stage.

5. Retighten fasteners to 60-80 N-m (44-59 lb-ft)

during the second stage.

INTAKE MANIFOLD PROCEDURE

1. Clean and inspect the mounting surfaces of the

intake manifold and the cylinder head. Both sur-
faces must be clean and flat (Figure 10.1).

2. Clean and lightly oil the manifold bolt/stud

threads.

3. Install a new lower intake manifold gasket.
4. Position the lower intake manifold to the cylinder

head.

5. Install retaining bolts/studs finger tight.
6. Tighten all bolts/studs to specifications in the

tightening sequence shown:

• First pass = 7=10 N-m (5-7 lb-ft).
• Final pass = 26-38 N-m (19-28 lb-ft).

Figure 10.1 — Intake Manifold Installation

CYLINDER HEAD PROCEDURE

1. Position head gasket on the block (Figure 10.2).
2. Position cylinder head to cylinder block.
3. Install 10 cylinder head bolts in numerical

sequence. Tighten to 70 N-m (52 lb-ft) in sequence.
Retighten to 70 N-m (52 lb-ft) in sequence. Then
turn all head bolts an additional 90 - 100 degrees
in sequence.

10-1

Standby Generator Sets

Maintenance

Maint005 Rev.

0 08/05