Dryer pre-start checks, Chapter 5 dryer pre-start checks, Inspect the metering rolls set control switches – GSI Outdoors 100 SERIES DRYER PNEG-552 User Manual

Page 22: Inspect the metering rolls, Set control switches

Advertising
background image

22

PNEG-552 100 Series Dryer

5. Dryer Pre-Start Checks

Before the dryer is filled, thoroughly inspect the unit and check the operation of the dryer as follows.

Inspect the Metering Rolls

Figure 5A Asco Safety Shut Off Valve

Open all metering roll access doors and inspect each compartment for any bolts, nuts or other foreign
material, that may cause possible jamming of the metering rolls.

Set Control Switches

Moisture Control Switch

OFF

Moisture Control Thermostat

200°

Load Switch

OFF

Unload Switch

OFF

Fan Switch

OFF

Burner Switch

OFF

Out of Grain Timer

1 MINUTE (Reset to 8 Minutes after testing)

Load Delay

30 SECONDS

Unload Delay

30 SECONDS

Metering Roll Speed

LOW AND HIGH SPEED SETTINGS PUT ON ZERO

Dry Timer

60 MINUTES

Cool Timer

20 MINUTES

Unload Timer

10 MINUTES

Mode Switch

CONTINUOUS FLOW

Before attempting to operate the dryer make sure all safety shields are in place,
all bottom clean-out and rear access doors are closed and all personnel are
clear of the dryer.