To isolate the t1 or t2 data path, Sun proprietary/confidential: internal use only – Sun Microsystems 6900 User Manual

Page 114

Advertising
background image

94

Sun StorEdge 3900 and 6900 Series 2.0 Troubleshooting Guide • March 2003

Sun Proprietary/Confidential: Internal Use Only

■

When you insert a loopback connector in to the T port, no green light appears to
indicate a proper insertion. However, the test will run and be valid.

■

If only one of the links has failed and the I/O is traveling over the remaining link,
I/O is automatically routed over the repaired link by the switch after the failed
link is replaced and recabled. No manual intervention is required.

■

If both links have failed and a LUN failover has occurred, you must manually run
a

failbackt3path

command to return the paths to their optimal state, after you

repair and recable the links.

▼

To Isolate the T1 or T2 Data Path

1. Run

linktest

from the Storage Automated Diagnostic Environment for a guided

isolation procedure.

2. After replacing the failed FRU, run

failbackt3path

, if needed.

Advertising