TRANSFORMER (CONTINUED)
STEP 3: CHECK FOR 24 VAC AT TRANSFORMER CN4 PLUG ON CONTROL BOARD.
Condition:
• CN4 is plugged into control board.
• On/Off switch is on.
Insert meter probes into back of CN4 plug on pins 3 and 4 (blue and yellow wires) with CN4
plugged in and power on.
STEP 3
24 VAC FROM TRANSFORMER
IF…
THEN
24 VAC is not present
replace transformer if Steps 1 and 2 were performed and results were successful.
24 VAC is present
continue to Step 4.