4] installation of network equipment in an fl-net – Sharp Z-336J User Manual

Page 215

Advertising
background image

15-61

Chapter 15: Appendix

15

[4] Installation of network equipment in an FL-net

Shown below is an example installation of network equipment in an FL-net system.
1. Install a transceiver in a metal box using a wooden board for insulation. The box must have a class D

ground.

2. Run the transceiver cable to the controller control panel through metal conduit. Provide a class D

ground for the conduit.

3. Install a hub inside the controller control panel using a metal, U shaped bracket. Use a hub that is

electrically isolated from the metal mounts, such as by using rubber feet. Ground the hub mounts to
the control panel. The control panel must be provided with a class D ground.

Installation example of network equipment in an FL-net

Controller control panel

Transceiver installation box

Transceiver isolation plate
(wooden board)

Coaxial cable

Transceiver cable

(AUI cable)

Transceiver cable

(AUI cable)

Transceiver main housing

Conduit

Conduit

U shaped hub mounting bracket

Hub

10BASE-T cable

Controller control panel