INSTALLATION INSTRUCTIONS FOR MASONRY APPLICATION

WARNING: Before starting the installation, the masonry chimney

must be inspected by a qualified chimney sweep.

The following requirements must be respected:

1. The chimney must be absolutely clear of any soot residue or creosote.

Check for cracks, loose or missing bricks that could inhibit correct

installation of the liner.

2. The clearance to combustible must be a minimum of 1” between the

outside of the masonry and any wood framing or loose insulation.

3. The chimney must be built in accordance with the current building

code.

4. No other appliance can be connected to the same chimney.

5. The clearances to combustible for the BISTMA30 connectors are 2”

on the side and bottom and 16” at the top.

6. The connector parts are not necessary if the connection between the

insulated length and the stainless steel liner is done within the masonry

chimney.

Installation:

The chimney must be relined with a stainless steel liner model TUBINOX

or Projet SS of the same diameter as the outlet of the fireplace.

For connection at 30º angle, a special connector (BISTMA30) must be

used to connect the liner to the insulated chimney.

* IMPORTANT NOTE - The use of a 45º connector (BISTMA) is ap-

proved for use in Canada ONLY. Installations in the USA must use the

30º connector (BISTMA30).

Follow these steps:

1- Position the fireplace in its location. Temporarily install the S2100+

elbow on the top of the fireplace and, using a level, mark with an oval

the location where the flue liner will enter the masonry chimney.

2- In the middle of the oval, drill a hole in the masonry chimney at 30º.

3- Increase the size of the hole until a 30º TUBINOX liner elbow can be

easily slipped through.

4- Slide the liner down from the top of the masonry chimney until you

reach the hole level.

5- Slip through the hole a 30º liner elbow and connect it to the liner.

6- Add a small liner section to the liner elbow which will allow the liner to

extend at least 12” (measured at the top of the liner) from the masonry

chimney.

7- Seal the opening around the liner with high temperature refractory

cement.

8- The next steps must be done in the following order:

See typical installation illustrated below.

A. Select the S2100+ length that will fit between the elbow and the liner

so that it will slide at least 2” over the liner section (You may need to

cut the liner for a better fit).

B. Take that section and the BISTMA30 cover and slide it over the liner.

Make sure you have enough opening to be able to install the S2100+

elbow without difficulty.

C. Install the 30º elbow on the fireplace.

D. Slide the length section back down on the elbow and twist lock the

two together.

E. Pull the cover down over the length and install the insulation pad over

the liner; be careful to cover the liner completely.

F. Slide back the cover over the insulation and fix it in place using the 3

metal screws supplied.

Figure 32

1” Clearance

Firestop

TUBINOX or Projet SS

Stainless Steel Liner

TUBINOX or Projet SS

Liner Must Slide at

Least 2” Inside Length

Insulated

Length

Masonry Chimney,

New or Existing

High-Temp.

Cement

Insulation Pad &

Cover (BISTMA or

BISTMA3U)

3 Screws

* 30°

S2100+ / GX

Insulated Elbow

6’ 8”

NOTE: DIAGRAMS & ILLUSTRATIONS ARE NOT TO SCALE.