INSTALLATION

RECEIVING & UNPACKING EQUIPMENT

1.

Check packing slip to ensure ALL material has
been delivered.

2.

All material shortages are to be reported to
NORTEC within 48 hours from receipt of
goods. NORTEC assumes no responsibility
for any material shortages beyond this period.

3.

Inspect shipping boxes for damage and note
on shipping waybill accordingly.

4.

After unpacking, inspect equipment for
damage and if damage is found, notify the
shipper promptly.

5.

All NORTEC products are shipped on an
F.O.B. factory basis. Any and all damage,
breakage or loss claims are to be made
directly to the shipping company.

PRE-INSTALLATION CHECKPOINT

1.

Ensure that available voltage and phase
corresponds with humidifier voltage and phase
as indicated on humidifier’s spec label (see
Figure #1).

2.

Ensure that the dedicated external disconnect
is of sufficient size to handle the rated amps

as indicated on the spec label. Refer to local
codes.

3.

Report any discrepancy immediately.

BASIC HUMIDIFIER CONFIGURATION

NORTEC NHSC / NHDI humidifiers share a

modular sheet metal cabinet. Each unit has a right
side electrical compartment. Each electrical
compartment has a hinge-down front door which is
removable from any partially or fully opened position.
Each electrical compartment has a screw-mounted
right side cover which can open for ease of electrical
connection. For safety, the door when closed keeps
the side cover from being opened.

Single units have a plumbing compartment

attached to the left side of the electrical. Double units
have a second plumbing compartment. Each
plumbing compartment has a hinge-down front door.
For safety, the door must be closed in order to engage
the safety interlock. To avoid any danger, never
operate the humidifier with a door off.

To open the doors, unlock, lift door up slightly and

pull top of door forward. Door will hinge 180 degrees
and hang straight down. To remove door, swing door
parallel to floor. Then lift up slightly and out. To
reinstall door, hold parallel to floor and insert hinge
pins at bottom.

- 1 -

Scale
Collector
Tank

Drain
Valve

Steam Outlet
1.75" O.D.

Spec
Label

Keypad
Display

Optional SSR
Cooling Fans

Power and
Control
Wiring

Water

Supply

NOTE: NHDI does not have the scale collector tank.

Figure #1

NHSC / NHDI Series Humidifier

Min. 12"

Min. 10 Degree Slope

Trap

* See Section On

Condensate

Return Line

NOTE: Trap must be 3' minimum down from steam distributor.
If not, condensate must be routed to drain.

Figure #2